Calculatorism

Earned Value Management Calculator

Enter planned value (PV), earned value (EV) and actual cost (AC) to compute cost/schedule variance and CPI/SPI, judging whether the project is over/under budget and ahead/behind.

Input Data

Planned Value
HK$
Earned Value
HK$
Actual Cost
HK$

Results

CV = EV − AC; negative means over budget.
HK$-5,000
SV = EV − PV; negative means behind schedule.
HK$-10,000
CPI = EV ÷ AC; >1 cost-efficient, <1 over budget.
0.9474
SPI = EV ÷ PV; >1 ahead, <1 behind.
0.9

At a glance:Earned Value Management (EVM) unifies cost and schedule on one baseline — earned value (EV), the budget of work actually done. Planned value PV is the budget scheduled by now; actual cost AC is what was really spent. Cost variance CV = EV − AC and schedule variance SV = EV − PV show absolute over/under; the ratios CPI = EV ÷ AC and SPI = EV ÷ PV are unitless and comparable across projects and time (CPI/SPI > 1 = cost-efficient/ahead, < 1 = over/behind). EVM's value is early warning mid-project, not just at close-out.

Formula

Cost variance: CV = EV − AC.

Schedule variance: SV = EV − PV.

Cost performance index: CPI = EV ÷ AC.

Schedule performance index: SPI = EV ÷ PV.

$$CV = EV - AC$$
$$SV = EV - PV$$
$$CPI = \frac{EV}{AC}$$
$$SPI = \frac{EV}{PV}$$

How to Use

  1. Enter planned value PV (budget scheduled by now).
  2. Enter earned value EV (budget of work done).
  3. Enter actual cost AC (what was spent).
  4. The tool returns CV, SV, CPI and SPI with a note.

EVM example (PV fixed 100,000)

EVM example (PV fixed 100,000)
EVACCV / SVCPI / SPIRead
90,00095,000−5,000 / −10,0000.95 / 0.90Slightly over and behind
100,000100,0000 / 01.00 / 1.00On time and on budget
110,000100,000+10,000 / +10,0001.10 / 1.10Ahead and saving
80,000100,000−20,000 / −20,0000.80 / 0.80Clearly over and behind

CPI/SPI > 1 = good cost/schedule efficiency; < 1 = over/behind. Indices are unitless ratios, easier to compare than absolute variance.

Case Studies

One check: over budget or behind?

IT project budget HK$100,000; at midpoint PV = 100,000, EV = 90,000, AC = 95,000.

CV = 90,000 − 95,000 = −5,000 (over); SV = 90,000 − 100,000 = −10,000 (behind).

CPI = 90,000 ÷ 95,000 ≈ 0.95, SPI = 90,000 ÷ 100,000 = 0.90 — slightly over budget and behind; act early.

FAQ

What is the difference between CV and CPI?

CV is the absolute money over/under (EV − AC); CPI is the ratio (EV ÷ AC). CV shows the size of the problem, CPI shows efficiency and is comparable across projects of different sizes.

Can CPI and SPI disagree?

Yes — a project can be cost-efficient (CPI > 1) but behind (SPI < 1), or ahead but over budget. Read both to see the real picture.

Is EVM only for big projects?

No. Any work with a budget baseline and tracked progress can use it; it is common in construction, IT and PMP study.

What does CPI < 1 mean for the future?

It means each dollar spent returns less than a dollar of value; unless corrected, the project will likely finish over budget. EVM's early warning lets managers intervene.

Related Tools

References

Content review: Calculatorism Finance Team. Results are for reference only; please refer to the relevant authorities for the official figures.

Found a problem with the results?

If this calculator's result is wrong, or you have any question about the calculation logic, please let us know. You are viewing:Earned Value Management Calculator(/finance/earned-value-management)。